Skip to main content

Replace Docks 12, 13, and 14

Project Location:Oyster Point Marina
Status:Design and Engineering
Inititial Funding:November 18, 2020
Estimated Completion:TBD
Description:The City of South San Francisco entered into an agreement with the District to manage the OPM.  As part of the agreement, the District must replace docks 12, 13 and 14 by December 31, 2024. 
Justification:Docks are over 30 years old and need to be replaced.
Strategic Goal/Operating Impact:1) Comprehensive Long-Range Planning Guides District Actions and Decision-Making.
 2) Infrastructure Improvements are Guided by Comprehensive Long-Term Planning. 

UPDATES:

July 19, 2023 Dreding permit approved by BCDC .  Board approved General Manager permit execution.

Moffatt and Nichol working on design and engineering for the replacement of Docks 12, 13 and 14.  Dredge need areas have been identified after conducting bathymetric bottom survey.  Public workshop was help on July 8, 2021 at 6:00 PM.  On July 21, 2021 Board approved moving forward with Maintenance Dredging the East Basin to -8".  Moffatt and Nichol teams are working on all permitting and timelines. 